PROJECT DATA

University of Economics and Business in Vienna: A Masterpiece of Design & Architecture

Project: University of Economics and Business, Vienna, Austria

Contractor (and Architects): Franz Leski (construction manager), Zaha Hadid Architects (Hamburg), building company Granit (Graz) 

MEVA Systems: wall formwork and special design Mammut 350,  circular formwork Circo, support Frame MEP, slab formwork MevaFlex, Triplex, push-pull props

Formwork Engineering: MEVA Austria and Germany

 
 
1
2
3
4
5
6
7
8
9
10
11
12
13
 

PROJECT

A Masterpiece of Design & Architecture

A Major Challenge to Formwork Suppliers

Founded in 1898 as the Imperial Export Academy to prepare students for employment in international trade, the academy soon took on the characteristics of a university and in 1975 became the Vienna University of Economics and Business. Built for 10,000 students, the university is much too small for the 23,000 students that today attend Central Europe’s largest university of economics. Hence, a new campus is being built in the heart of the Austrian capital and planned to be inaugurated in 2013. Designs by esteemed architects from Europe and Japan were selected for the six new buildings on the campus and four of them are erected using MEVA formwork and formwork solutions.

The Library and Learning Center (LLC):  Architectural highlight and hub on the Campus
Designed by Zaha Hadid Architects, the new LLC is a masterpiece of architecture. Located in the centre of the campus and intended to be more than a classical library, the LLC will connect counselling and library services. Apart from books, the LLC will also offer working places, service centres and lounge rooms. With its facilities open for students and employees 24 hours a day, 365 days a year, the LLC will be the central communications and information hub on the campus.

Different cores, walls inclined at different angles, inclined and rounded corners
The LLC has five cores, each with a different complex geometry. The core walls are inclined at different angles and so are the corners which are also rounded with different radii. MEVA has developed and uses both standard and special formwork, or a combination of both, to meet the forming requirements for these complex building parts. Steel formwork, for example, is used for rounded corners if required for structural reasons. Trapezoidal areas of inclined cylindrical corner areas are poured with special Mammut 350 wall formwork panels and special designs of MEVA’s circular column formwork Circo are used for the tilted and rounded corners.

Walls with fanned out board patterns and inlays with smooth architectural concrete surface
The inclined core walls are poured with an architectural concrete surface and a board pattern is applied to them. The pattern is achieved with wooden boards attached to the Mammut 350 panels. Since the front walls are inclined at different angles, the side walls have four different angles and are wider at the top than at the bottom. This requires detailed planning and a little “trick“ in order to achieve a consistent board pattern on the side walls. On the left and right of the side wall, the boards, and thus pattern, are parallel to the adjoining front wall. Since the front walls are not parallel, the board pattern on the left of the side wall is inclined at another angle than the pattern on the right. To compensate for the different angles, the pattern is fanned out in the middle section of the side wall. The boards used for the fanning out section are wider at the top than at the bottom and their width ranges from 8 to 12 cm, depending on the fanning out area they are used for. The boards of a specific fanning out area always have the same size to achieve a homogenuous and consistent fanning out pattern and, what’s more, MEVA engineers planned these patterns to be consistent on the entire multi-storey wall from the ground to the top. The boards used for rounded walls are generally 8 cm wide.

The core walls have so-called inlays. They are areas with a smooth architectural concrete surface that optically interrupt the board pattern and are achieved with the alkus all-plastic facing that is standard in all MEVA formwork systems.

Another specialty are the canyon walls between the cores. Mostly consisting of beams and parapets, the canyon walls are also inclined and curved with different radii. They are formed with the Mammut 350 panels and then plastered. Rounded parts of the canyon walls are formed with special timber formwork.

Comprehensive on site support and careful detailing
The LLC is built by the Austrian contractor Granit from Graz, Austria. Work and staff are supported on site by MEVA Austria while all formwork solutions for MEVA and non MEVA standard and special formwork are planned by Application Engineering at the German MEVA headquarters.

 
  • MEVA Expertise & References

    MEVA Expertise & References

    Referencen for Projets in Commercial & Residential Construction, Architectural Construction, High-Rise Construction and Civil Engineering Construction

  • Reservoirs with a capacity of 4.5 billion gallons are being built to increase the drinking water reserve

    Reservoirs with a capacity of 4.5 billion gallons are being built to increase the drinking water reserve

    As Qatar’s population and economy keep growing and water demand is increasing, the Qatar General Electricity & Water Corporation (KAHRAMAA) has launched an ambitious water project to provide increased water storage capacities and extend the supply reserve of drinking water from two to seven days.

  • South Canal Bridge, Ontario: With no crane possible at busy Hwy 400, MevaLite handles the job with ease

    South Canal Bridge, Ontario: With no crane possible at busy Hwy 400, MevaLite handles the job with ease

    One of Ontario’s busiest transportation corridors, Highway 400, began a major expansion project through Kings Township in late 2016. This $79.3 million dollar (CAD) project includes the widening of the highway from three to six lanes in each direction for a two mile stretch and also entails safer on and off ramps, the expansion and realignment of culverts, and the replacement of two bridges − one of them the South Canal Bridge.

  • A Brand-New Theater for the Cincinnati Shakespeare Company

    A Brand-New Theater for the Cincinnati Shakespeare Company

    The new theater is called The Otto M. Budig Theater and located in Cincinnati’s Over-The-Rhine district. When completed, it will become the last section of the planned “Classical Arts Corridor” in Cincinnati, which also includes a Music Hall, School for Creative and Performing Arts, and a park.

All Plastic Facing alkus
MEVA Frame Profile
... more than just formwork
  •  Select language

    Select continent and country. Language selection optional.

  •  Contact
  •  Search

    Search on our website.

  •  Newsletter

    Subscribe to our monthly newsletter.